Construction Analysis Assignment 3

ABPL20033 - Construction Analysis, Semester 2 - 2018 Dr Alberto Pugnale – Subject coordinator Dr Sofia Colabella – Senior Tutor Dion Keech – Tutor Emma Kelly, 950391, 17.10.2018 Queenscliff House, T15 ASSIGNMENT 3
FLIPBOOK SECTION 3D: Layers of information
1. Structural Systems, below ground The proximity to the beach and the views available at the site influenced the design of the house significantly. The layout of the rooms, the large glazing throughout the house and the open plan living areas capture the exteriour and enhance the feeling of it being a beach house, which was requested by the clients. The harsh environmental conditions and the large spans required for large glazing dictated the use of material, eg. galvanised steel.
Vertical Structural systems, below ground Horizontal
Pad Footing 300 diameter, 150 mm deep poured concrete
Stumps reinforced 100 x 100mm prefabricated concrete
Mass Concrete Pad 600 x 600 x 400mm poured concrete
Columns square hollow sections galvanised steel to be later installed
Stripfooting reinforced 450 x400m poured concrete 4 wire mesh, starter bars
Stumps 100 x 100 prefabricated concrete
Mass concrete pad
Pad footing
ABPL20033 - 2018, Emma Kelly | 950391 |T 15, Dion Keech
Strip footing reinforced concrete
2. Structural Systems, above ground
Primary Structure
Steel frame - Universal Beam, Parallel Flange Channel, Eaqual Angle Concrete - insitu wall Timber - brearers, joists (groundfloor)
Secondary Structure
Timber - stud walls, rafters, soldiers, battens, I- joists
Strap bracing - 30 x 0.8 galv. steel Ply bracing - 6mm F11 plywood
Ground Floor Horizontal Structural Systems, above ground
First Floor Vertical Roof
The steel framing was designed by the engineers in order to achieve large spans and allow for large glazed areas. This is to capture the view and visually connect the building parts. A timber floor was later introduced in order to achieve the necessary green star rating, as the new planning scheme allowed for a loophole.
Rafters 2/240 x 45 Hyspan Laminated Veneer Lumber at 1200 centres
Square Hollow Section 89 x 89 x 4 Parallel Flange Universal Beam Channel 125 x 65 250 37
Stud wall 90 x 45 studs at 600 centres
Battens 90 x 35 MGP 10 at 900 centres
I-joists 360x 90 at 450 centres
Strap bracing 30 x 0.8 galv steel
Square Hollow Section 150 x 150 x 6 galvanised steel
Insitu concrete wall Floor joist 45 x 90 MGP10 Bearers 2/45x90 MGP
Ply bracing 6 mm ply
3. Internal (non-load bearing) partitions Fixed Internal Partitions
Internal non load bearing studwalls Plasterboard lining Frosted glazing - “Matelux� Toughened grade A safety glass pivot doors
Plasterboard ceiling
Non-loadbearing stud walls
The internal partitions separate different areas according to their program. They mediate the privacy of the occupants and organise every day life. The frosted glazing separating the en-suite shower and the corridor is an interesting way to separate a very private from a very public area. It blurres the lines of what is intimite and a thouroughfare. The plasterboard lining allows for even paint finishes that can be changed over the years, the pivot doors allow for a smooth opening in the walls without a bulky frame. All these methods make for a smooth and simple finish thorughout the house.
Frosted glazing
Frosted glazing Pivot door
Plasterboard walls
4. Environmental Protections
galvanised steel to prevent corrosion due to moisture Horizontal
Waterproofing
Environmental Protections
paint - Tasman Terrasand clear hydrophobic sealer for concrete walls sarking - 55mm Bradford foil
Vertical Insulation
plasterboard - waterproof in wet areas roof - R4.0 gold batts between rafters, 55 mm Bradford foil walls- R3.2 Bradford Soundscreen batts, 2 x R1.6 batts floor - 2.5 Bradford Soundscrren batts
The largest part of the environmental protections throughout the house are being kept invisible from the outside. The insulation and sarking is within the building envelope. The sealing paint finish on the concrete wall is translucent and doesn’t interfere with the concretes appearance.
55 mm Bradford non-combustable blanket insulation
R 4.0 Bradford gold batts between rafters R 2.5 Bradford Soundscreen batts Hydrophobic sealer on concrete
R 3.2 Bradford Soundscreen batts
R 2.5 Bradford Soundscreen batts
5. Mechanical and electrical systems
hot water - shower, sinks
The electrical layout is made to meet the occupants needs, e.g.. power-plugs or lightswitches next to the bed, plugs in the kitchen and bathroom for appliances etc. The hydronic heating system is chosen to have the least influence on every day life as it is non intrusicive. Also, it is laid out to allow for an optimal use of energy when heating the rooms. Positioning the trenches under the windows allows for a thorough heat transfer throughout the rooms. As both systems are hidden within the building fabric, the spaces didn’t need to be organised in accordance to the mechanical and electrical systyems. The trenches also allow for the large glazing areas, as they don’t need walls to be mounted on.
Water Supply
Essential services
cold water - shower, sinks, toilet sewage - from sinks, toilet,shower, etc. to sewer line
Electrical layout throughout roof structure for eventual downlights or pendant lights
hydronic heating - closed loop system hot water supply, heat emitted through radiator, cold water return connection from grid to property, to switch board, supply throughout house on seperate circuits controlledand manageable by fuses
Boiler or other hot water system
Hydronic heating trench and connections
boiler and trench connection Electrical layout to powerplugs in bedroom
Cold and hot water connection tosho
Cold and hot water connection to kitchen
hydronic trench and distribution (retrieved from: www.purmo.com)
SWITCHBOARD HW HOT WATERSYSTEM
HH HYDRONIC HEATING CLOSED LOOP
hydronic trench running along window front
6. Physical Enclosures systems
Metal roofsheet
138mm x 19mm dressed, ship lapped, Spotted Gum cladding
External cladding
“Matrix” Façade Panels, 8mm thick, 2390x590 panels
roof sheets
Metal roof “Trimdeck Hi Ten” sheets
150 x 300 boxgutter
parapet capping
galvanised steel capping finished with dulux paint
frame, sill, glazing, flashing
tassie oak frame
Enclosure Systems Wooden cladding to enclose and seal building
blackbutt sill Window and Sliding doors
toughened glass Kitchen bench
The physical enclosure system consists of different components. The timber cladding greys over time and reflects the intention of the architects to create a building that blends in with the sanddunes and create a true beach house. The cement cladding on the kitchen indicates a change of program in the inside. The gutter is hidden within the roof structure and maintains a thin roof profile, also enabling the building to sit within the landscape almost naturally. Roof sheet Windows and Sliding door
Parapet capping
Cement cladding
Spotted gum cladding


Flipbook Section 2D Eunice Chow 2020
The University of Melbourne Bachelor of Design Construction Analysis Semester 2-2020 Assignment 2 Lake Wendouree House Section 3D
The University of Melbourne Bachelor of Design Construction Analysis Semester 2-2020 Assignment 2 Lake Wendouree House Section 3D Less
ABPL20033 Construction Analysis, Semester 2 - 2020 Dr Alberto Pugnale, Subject coordinator Dr Sofia Colabella, Senior Tutor Anastasia Sklavakis Chow Tsz Yu Eunice, 988725, 27/09/2020 Lake Wendouree House, Tutorial 6 ASSIGNMENT 2 FLIPBOOK SECTION 2D: construction stages, details and annotations Cover image, photo by John Wardle Architects
2 3 4 3D Ground First - Floor Floor A 7.04 Electric screwdriver is used 7.03 to fixed to place, reference B 7.01 Rough-in services in the kitchen area, such as to Gyprock from Google During inspection, spirit level is used to double check and prepare the downlight wires, cables for clipsals, water pipes for sinks, surface for plasterboard installation drainage pipes to sewer are brough in but not connect to Workers cleaning water any applicants yet. on site to prepare for the flooring. 7.02 Internal wall and ceiling insulation is finished in this stage. Insulation is critical in cellar that it needs to retain the After the rough-in is 7.01 set the plasterboard temperature different from adjacent rooms. Double will be installed, and C insulation is required, also to provide acoustic privacy. wires will runs through the walls and wait for 7.03 Inspection is carried out to double check any defects connect to applicants before plasterboards are constructed. Timber studs should 7.01 in next stage. 7.02 be straight without gaps, all uneven surfaces and dirt should be removed. Stretcher bond brick wall 7.04 Plasterboard or villaboard is glued and nailed to Cavity wall timber studs every 300mm, and 150mm on the edge. 6mm villaboard is fully taped and scrimmed D Although ceillar wall is installed earlier in stages, it is finished 50mm insulation is with all the other internal partition in stage 7. The detail a high density drawings shows the process of constructing cellar wall as a tongue and groove polystyrene epoxy highly private room, with advanced acoustic privacy and fixed to joints insulated for wine storage. Cellar is double insulated with 88mm Bradford Soundscreen plus R2.5 13mm plasterboard is water resisitant E External pipes such - as hot water pipes, 3D air-conditioner water pipes are designed ABPL 20033 Construction Analysis 2020 Sem2 exposed to outdoor. Assignment 2: Flipbook Secion 2D Student Name: Eunice Chow (988725) Drawing: Stage 7 Internal partitions, ceiling structure, rough-in services, wall lining - Plan (Scale 1:50 at A3)
2 3 4 3D External ceiling speaker Ground First - fixed on first floor cantilever Floor Floor A 8.01 Clipsal controlling First Floor living area timber flooring electricity on first floor living area B 8.01 Flooring on the first floor living area is timber while the bathroom is laid with tiles to repels water. 8.02 Most of the furnitures in the kitchen area is built-in Worker fixing pipes to basin 8.06 according to joinery drawings by trade group. The outdoor area is laid in stone pattern. Upstairs living used 8.03 Except furnitures fix-off, wired for safety, such as smoke Trees are transported to site ready to be planted, following 8.02 select grade spotted gum timber flooring. alarm is also installed. landscape drawings. Wastes on the bench has started to clean up to prepare to be used. 8.01 C 8.04 The house mostly uses downlights as lighting fitout. 8.05 Paintings of walls and ceilings. Hardwired smoke alarm is required for safety 8.06 Landscape materials are brough in as a final touch. especially in kitchen area, according to AS 1670.1 Access panel Doors are installed in this stage to create privacy D through separating space. Exhaust fan grill is essential to keep 8.04 the bathroom ventilated prevent Lighting in cellar is relatively moisture damage appliances. dim that not much downlights are installed. Although there is skylight allowing natural light penetrate, but electric light is still important to prevent injury in bathroom area. 8.04 E Bathroom tiling used graniti fiandre - 3D Clipsal is needed to allow ABPL 20033 Construction Analysis 2020 Sem2 hoseholds to control the lighting Assignment 2: Flipbook Secion 2D Student Name: Eunice Chow (988725) Drawing: Stage 8 Finishing trades, joinery, appliances - Plan 8.04 Scale 1:50 at A3 Skylight on first floor bathroom
- Related publications
- Add to favorites
- MSDx_2020_Winter
- Bachelor of Design Studios and Subjects
- Construction
Construction Analysis
Subject coordinator Dr Sofia Colabella
Tutors: Aleks Baltovski, Senior Design Manager at John Holland; Jim Commadeur, director at Jim Commadeur Architects; Anastassia Sklavakis, Architect at Six Degrees Architects.
This subject explores the idea of construction as a process linking structural principles, materials and building techniques strategically. Using a set of two-story houses as case studies, Construction Analysis reviews the anatomy of building elements, components and systems by relating architectural choices to technological and performance requirements.
Having completed this subject, it is expected that the student be able to: (1) identify and follow the logics of construction; (2) familiarise with the conventions and challenges of technical representation; (3) observe how architectural design and technological requirements inform each other; (4) appreciate the relationship – or the distance – between architectural design, construction and the principles underpinning environmentally sustainable design; (5) transform this appreciation into an interpretative framework for the organization of small- to medium-scale architectural practice.
Flipbook Section 2D
Layers of information.
Construction 2020_winter
- MSDx Summer 2022
- MSDx Winter 2022
- MSDx Summer 2021
- MSDx Winter 2021
- MSDx Summer 2020
- MSDx Winter 2020
- Search MSDx
- Current Students
sql server reporting services upload file
- presentation
- problem solving
- rewiew prompts
- websites tips

Category : Moscow Metro
Subcategories.
This category has the following 18 subcategories, out of 18 total.
- Quality images of Moscow Metro (82 F)
- Gallery pages of the Moscow Metro (1 P)
- Moscow Metro in art (2 F)
- Maps of Moscow Metro (4 C, 51 F)
- Panoramic views of Moscow Metro (96 F)
- Art in Moscow Metro (11 C, 255 F)
- Construction of Moscow Metro (2 C, 8 F)
- Events of Moscow Metro (4 C, 8 F)
- Fossils in Moscow Metro (7 C, 1 F)
- History of Moscow Metro (17 C, 13 F)
- Infrastructure of Moscow Metro (32 C, 135 F)
- Lines of Moscow Metro (22 C)
- People associated with Moscow Metro (12 C, 7 F)
- Police officers in Moscow Metro (15 F)
- Tickets of Moscow Metro (4 C, 27 F)
- Trains of Moscow Metro (9 C)
- Videos of Moscow Metro (62 F)
- Russian FOP cases/Moscow Metro (93 P)
Pages in category "Moscow Metro"
This category contains only the following page.
- Московский метрополитен
Media in category "Moscow Metro"
The following 19 files are in this category, out of 19 total.

- Metro de Moscú 1.webm 32 s, 1,920 × 1,080; 12.26 MB

- Rapid transit in Russia
- Rail transport in Moscow
- Public transport in Moscow
- Third rail electrification in Russia
- Department of Transport and Road Infrastructure Development (Moscow)
- Public transport companies of Russia
- Unitary Enterprises of Russia
- Categories requiring permanent diffusion
- Uses of Wikidata Infobox
- Uses of Wikidata Infobox with maps
- Pages with maps
Navigation menu
- Preplanned tours
- Daytrips out of Moscow
- Themed tours
- Customized tours
- St. Petersburg
Moscow Metro
The Moscow Metro Tour is included in most guided tours’ itineraries. Opened in 1935, under Stalin’s regime, the metro was not only meant to solve transport problems, but also was hailed as “a people’s palace”. Every station you will see during your Moscow metro tour looks like a palace room. There are bright paintings, mosaics, stained glass, bronze statues… Our Moscow metro tour includes the most impressive stations best architects and designers worked at - Ploshchad Revolutsii, Mayakovskaya, Komsomolskaya, Kievskaya, Novoslobodskaya and some others.
What is the kremlin in russia?
The guide will not only help you navigate the metro, but will also provide you with fascinating background tales for the images you see and a history of each station.
And there some stories to be told during the Moscow metro tour! The deepest station - Park Pobedy - is 84 metres under the ground with the world longest escalator of 140 meters. Parts of the so-called Metro-2, a secret strategic system of underground tunnels, was used for its construction.
During the Second World War the metro itself became a strategic asset: it was turned into the city's biggest bomb-shelter and one of the stations even became a library. 217 children were born here in 1941-1942! The metro is the most effective means of transport in the capital.
There are almost 200 stations 196 at the moment and trains run every 90 seconds! The guide of your Moscow metro tour can explain to you how to buy tickets and find your way if you plan to get around by yourself.

IMAGES
VIDEO
COMMENTS
Service pipes are arranged and organized by plumbers, they are usually 500mm higher than the earth level since the concrete floor slab will be poured later and the floor level will be rised. They...
Name: Jackson Comben Student Number: 834398 Blinding minimum 200mm into clay STAGE 01 SECTION Scale 1:50 | p. 2 Stage 02 Ground Floor Structure In constructing the ground floor slab and its...
TEMPORARY TIMBER SUPPORT USED TO HOLD UP B3 310UB32. LBWS TILTED UP AND SUPPORTED BY 30X0.8MM CROSSED STRAP BRACING. BRICK WALL LAID IN STRETCHER BOND PATTERN. EXPANSION JOINTS LOCATED AT MAX 7M ...
Construction Analysis Assignment 2 - Flipbook Section 2D by Will Scobie - Issuu Browse short-form content that's perfect for a quick read Purchase your next favourite publication Categories...
Construction Analysis - Assignment 2 - Construction Stages, Details and Annotations by Louis Zhang - Issuu Browse short-form content that's perfect for a quick read Purchase your next favourite...
ABPL20033 Construction Analysis Assignment 2: Flipbook ABPL20033 - Construction Analysis, Semester 2 - 2018 Dr Alberto Pugnale - Subject coordinator Dr Sofia Colabella - Senior Tutor...
Welcome to Issuu's blog: home to product news, tips, resources, interviews (and more) related to content marketing and publishing. ... Construction Analysis Assignment 2. ABPL20033 ...
construction analysis - abpl20033 assignment 2. tutor : mark lam time : wednesday, 05.15 - 07.15 pm. nesia cahyono 813807. plan. stage 1 - 12. section
03 Wall and ceiling on all floors using dry wall method (water-. ASSIGNMENT TWO: FLIPBOOK SECTION 2D CONSTRUCTION STAGES, DETAILS AND ANNOTATIONS Drawn by: Celina Supurnami Yaputra 813602 Project ...
Flipbook Section 2D In this assignment, the construction process of a case study is thoroughly descripted; the flipbook section assignment subdivides this process into 8 stages to emphasise the logic and sequence of construction. Grace Flood Yupeng Gao
ABPL 20033 - CONSTRUCTION ANALYSIS ASSIGNMENT 2 - THE FLIPBOOK SECTION 2D Dr Alberto Pugnale, Subject coordinator Dr Sofia Colabella, Senior Tutor Robert De Melis, Tutor ASSIGNED SECTION - 2C Ria Sharma ID - 1035954. SOIL REPORT STAGE 1 : SITE PREPARATION Demolition and Soil reports - The soil type for the lake Wendouree house has been Existing ...
Construction Analysis Assignment 1. Flipbook Section 'as-built' ABPL20033 - Construction Analysis, Semester 2 - 2019 Dr Alberto Pugnale, Subject coordinator Dr Sofia Colabella, Senior Tutor ...
Construction Analysis Assignment 3. ABPL20033 - Construction Analysis, Semester 2 - 2018 Dr Alberto Pugnale - Subject coordinator Dr Sofia Colabella - Senior Tutor Dion Keech - Tutor Emma ...
ABPL20033 - Construction Analysis, Semester 2 - 2019 Dr Alberto Pugnale, Subject coordinator Dr Sofia Colabella, Senior Tutor Robert de Melis, Tutor Hayley James, 1085215, 10/08/ Project 12 Architecture, Northcote House, 26 ASSIGNMENT 1 FLIPBOOK SECTION AS-BUILT: Assigned section and construction sequence
ABPL20033 - Construction Analysis, Semester 2 - 2022 Subject coordinator: Dr Sofia Colabella Tutor: Dr Robert De Melis Senior Tutor: Dr Alberto Pugnale Michelle Pranata, 1297719, Oct 22, 2022 Lake Wendouree House, Tutorial 08 ASSIGNMENT 3 FLIPBOOK SECTION 3D: Layers of Information 1. Structural Systems, below ground ASSIGNMENT 3: FLIPBOOK ...
by Eunice The University of Melbourne Bachelor of Design Construction Analysis Semester 2-2020 Assignment 2 Lake Wendouree House Section 3D Read the publication
Having completed this subject, it is expected that the student be able to: (1) identify and follow the logics of construction; (2) familiarise with the conventions and challenges of technical representation; (3) observe how architectural design and technological requirements inform each other; (4) appreciate the relationship - or the distance - ...
HIGH H1 95% Assignment 2 Flipbook. Plans and Sections with annotations referring to AS Standards. Assignment 2 Construction Analysis | ABPL20033 - Construction Analysis - UniMelb | Thinkswap
Read ABPL20033 Construction Analysis Assignment 2: Flipbook by Girvan Christian Tenggono on Issuu and browse thousands of other publications... Assignment 2. Flipbook Section 2D: construction stages, details and annotations Ziyang Yuan Vincent 2019 SM2.... CONSTRUCTION ANALYSIS FLIPBOOK SECTION 2D -ASSIGNMENT 2 BY - RIA SHARMA ID - 1035954.
Elektrostal, formerly (until 1938) Zatishye, city, Moscow oblast (province), western Russia.It lies 36 miles (58 km) east of Moscow city. The name, meaning "electric steel," derives from the high-quality-steel industry established there soon after the October Revolution in 1917. During World War II, parts of the heavy-machine-building industry were relocated there from Ukraine, and ...
Media in category "Moscow Metro". The following 22 files are in this category, out of 22 total. Emergency brake in Moscow Metro А-type car.jpg 960 × 1,280; 247 KB. Entering Ploschad Revolutsii.jpg 3,072 × 2,304; 1.44 MB. Ilya Masodov partisans Mrak tvoih glaz 01.jpg 2,940 × 3,920; 3.89 MB.
Parts of the so-called Metro-2, a secret strategic system of underground tunnels, was used for its construction. During the Second World War the metro itself became a strategic asset: it was turned into the city's biggest bomb-shelter and one of the stations even became a library. 217 children were born here in 1941-1942! The metro is the most ...
Find detailed information on Basic Chemical Manufacturing companies in Elektrostal, Russian Federation, including financial statements, sales and marketing contacts, top competitors, and firmographic insights. Dun & Bradstreet gathers Basic Chemical Manufacturing business information from trusted sources to help you understand company ...